Any crane lift within the City-Parish right-of-way must meet the following requirements:
A Street Closure Permit must be obtained for the area. All Street Closure Permit requirements must be met, including a petition from the residents directly affected.
A map or sketch of the area to be closed must be submitted with the permit.
The applicant must submit an indemnification agreement and proof of insurance at least thirty (30) days prior to the lift.
It is the responsibility of the permit holder to furnish, install and remove all required barricades and/or other traffic control devices as directed by the Traffic Engineering Division and/or the appropriate law enforcement agency. A traffic control plan must be submitted to the Traffic Engineering Division at least seven (7) days prior to the lift.
It is the responsibility of the permit holder to restore the street and surrounding area to its original cleanliness.
The violation of any City-Parish Ordinance during the course of the event shall result in the revocation of this permit.